Renovation Progress Spring-Summer 2008
Scope of the Work:
- Removal of rubberized surface and inspection of the bituminous concrete surface below.
- Repair of Bituminous Concrete (if necessary) and resurfacing of the track with a Red synthetic surface.
- Improvements to the long jump landing areas, including new sand and a larger landing area to keep current with safety standards.
- Improvements to the polevault landing areas, including concrete anchorages for the standards and a larger paved area for the landing system to rest on.
- Modifications to the discus cage to keep up with current safety standards.
- Modifications to the Jumping runways and resurfacing.
Aug. 11 - Rubberized Surface Complete - No Lines Yet |
Aug. 1 - Rubberized Surface First Coat. Discus Cage Completed |
|
|
|
|
|
|
|
|
|
|
July 14 - New Landing Sand Pits Constructed |
|
|
|
|
Bituminous Concrete Cures for 28 Days. |
|
|
June 20 - Blacktop layed down. |
|
|
|
|
|
|
June 18, 2008 - Crushed stones ready for Bituminous Concrete. Jumping pits dug out. |
|
|
June 10, 2008 - Bituminous Concrete Removed and Crushed Stone base improved |
|
|
![]() ![]() |
![]() ![]() |
Bituminous Concrete Removed and Discus Cage Stipped for Improvements |
|
|
June 2, 2008 - Work begins !!!!The rubberized surface is stripped to expose the blacktop. |
|
|












More piles of the old surface